Fund sync does not bring in start and end date
  • 29 Jan 2025
  • Contributors
  • Dark
    Light
  • PDF

Fund sync does not bring in start and end date

  • Dark
    Light
  • PDF

Article summary

When syncing a fund through the fund sync the funds Start date and End date are not brought in.


Answer:

We are currently investigating this issue.


Steps to replicate: 

1. In the Finance System: Add Start and End date to a fund.

2. In Foundation Cloud Grants to go Settings > Data Tools > Data Sync > Finance Fund Sync and run the sync process

3. Go to FIT > Control Panel > Admin > Sync > and run the sync process

4. In FIT go to Control Panel > Config > Funds > Open desired Fund

5. Notice start date and end date are empty 


Was this article helpful?